MSE wall BOQ template: bill of quantities for anchored MSE wall package.

This is the engineer-and-QS reference for structuring an anchored MSE wall package within a Malaysian tender BOQ. Items, units of measurement, and pricing notes are laid out to align with the conventions used on JKR, PLUS, LLM, KTMB, and major-developer tenders. Use this as a starting template; adapt the specifics (panel type, fill source, monitoring) to your project before issuing tender documents.

BOQ structure overview

A complete MSE wall package BOQ typically has 12-15 line items grouped into 5 sections. Each item carries a unit, a description, a quantity (filled in by the consultant) and a unit rate (filled in by the bidder). The five sections:

  1. Preliminaries - mobilisation, design, shop drawings, programme.
  2. Supply of components - precast panels, tendons, anchor blocks.
  3. Site works - foundation, erection, backfill, drainage.
  4. Finishes and adjustments - capping, architectural premium, joints.
  5. Monitoring and handover - instrumentation, baseline, defects period.

Full BOQ template

ItemDescriptionUnitPricing note
1. Preliminaries
1.1Design and shop drawings for anchored MSE wall, in accordance with BS 8006-1:2010, FHWA NHI-10-024, and JKR Standard SpecificationSumLump sum or per m² of wall face
1.2Mobilisation of plant and crew to siteSumLump sum
1.3Site office, storage compound, security fencingSumLump sum, duration-related
1.4Submission of design check, calculations, drawings for consultant reviewSumLump sum
2. Supply of components
2.1Supply and delivery to site of precast concrete facing panels, Grade 30 MPa, standard panel size per shop drawing, standard grey finishPer m² of facing area
2.2Supply and delivery to site of hot-dip galvanised steel tendons, diameter per design, length per shop drawingm (linear)Per linear metre of tendon, or by kg
2.3Supply and delivery to site of precast concrete deadman anchor blocks per shop drawingNo.Per unit (each block)
2.4Supply and delivery of geocomposite drainage blanket, minimum transmissivity 5 x 10-4 m/s, including overlapsPer m² of wall face
2.5Supply and delivery of perforated UPVC or HDPE collection pipe, 100-150 mm diameter, including bedding and outlet fittingsm (linear)Per linear metre of toe drain
2.6Supply and delivery of geotextile filter for toe drainPer m² of geotextile
3. Site works
3.1Excavation, levelling, and preparation of foundation areaPer m³ of excavation
3.2Cast in-situ concrete levelling pad, Grade 25 MPa, dimensions per shop drawingPer m³ of concrete
3.3Erection of facing panels including lifting plant, alignment, joint setting, temporary bracingPer m² of facing area
3.4Installation of tendons through facing panels, including connection torque to specificationm (linear) or m²Per linear metre of tendon, or per m² of wall face
3.5Installation of deadman anchor blocks in the retained-fill mass per shop drawingNo.Per block
3.6Supply and placement of crusher-run backfill (≥34° friction angle), placed in 200-300 mm lifts, compacted to 95% Modified Proctor MDDPer m³ of fill placed and compacted
3.7Installation of geocomposite drainage blanket against back of facingPer m² of wall face
3.8Installation of toe drain (excavation, granular bedding, pipe, geotextile, outlets, backfill)m (linear)Per linear metre of toe drain
4. Finishes and adjustments
4.1Cast in-situ capping beam, Grade 30 MPa, reinforced, dimensions per shop drawingm³ or m (linear)Per m³ of concrete or per linear metre of capping
4.2Architectural-finish premium for textured, coloured, or motif precast panels (above standard grey)Per m² of facing area, premium over base rate
4.3Drainage outlet connection to site stormwater networkNo.Per connection point
4.4Joint sealing between facing panels if specified (typically only on water-edge or aesthetic-sensitive walls)m (linear)Per linear metre of joint
5. Monitoring and handover
5.1Supply and installation of settlement plates, with riser pipe and reference capNo.Per plate installed
5.2Supply and installation of inclinometer casing (drilled, grouted, capped), depth per designm (depth)Per metre of inclinometer depth
5.3Supply and installation of piezometers (vibrating-wire or standpipe per design)No.Per piezometer
5.4Baseline survey and instrumentation readingsSumLump sum at handover
5.5Defects-correction period, quarterly inspection and reportingSumLump sum over defects-correction period
6. Provisional sums
6.1Provisional sum for ground improvement (PVDs + preload, stone columns, jet grouting) if soft-ground conditions encountered, to be activated by consultant instructionSumProvisional, paid against actual works
6.2Provisional sum for unforeseen variationsSumStandard provisional sum, typically 5-10% of base contract

Need a project-specific BOQ + cost band? Same-day response.

500+ projects since 1999. Send the wall geometry (height range, length, application) and we'll deliver an indicative BOQ with rates, programme, and project-specific notes.

WhatsApp → Discuss your project →

Pricing notes for QS reference

Per m² of wall face vs per m² of facing area

These are subtly different. Wall face is the exposed front area visible after construction. Facing area is the total area of facing panels including any below-grade portion or above-cap portion. For most projects they are similar but on walls with deep toe footings or extensive cap, the facing area can be 5-10% larger than the wall face. Specify which is intended in the BOQ description.

Backfill volume vs wall geometry

Backfill quantity is the volume of the reinforced-soil zone, typically 0.7-1.0 times wall height behind the facing. For a 6 m wall, 1 m linear length of wall: backfill volume ~5-8 m³. Note: this is engineered backfill within the reinforced zone only; bulk fill behind the reinforced zone is usually a separate earthworks BOQ item.

Tendon length per m² of wall

For anchored MSE walls, tendon length is typically 0.7-0.9 times wall height per tendon, with one tendon per panel typically. For a 6 m wall with 2 m x 1.5 m panels, that's ~4.5-5.5 m of tendon per panel, or roughly ~1.5-2.0 linear metres of tendon per m² of wall face.

Architectural-finish premium structure

Premium pricing varies by finish type:

  • Standard grey, smooth: base rate, no premium.
  • Standard grey, fluted or board-marked: 10-15% premium on panel rate.
  • Split-face or exposed aggregate: 15-25% premium.
  • Coloured pigment: 15-25% premium.
  • Cast-in motif or logo: 25-40% premium (depends on motif complexity).

Specify the finish in the BOQ description and let bidders price the premium explicitly, rather than bundling into a generic base rate.

Common BOQ mistakes to avoid

  • Bundling facing supply with erection. Splits cleanly: supply is a material item, erection is a labour-plus-plant item. Bundled, bidders can hide cost. Split, you get apples-to-apples pricing.
  • Forgetting drainage outlets. The toe-drain pipe is one item; the outlet connections to site stormwater are typically a separate item, often missed.
  • No provisional for ground improvement. Soft-ground sites need ground improvement; if the BOQ doesn't include a provisional sum, the contractor will either price-pad the base rate (overpaying if improvement isn't needed) or refuse to commit (delays).
  • Bundling instrumentation with civil works. Instrumentation is specialist equipment; keep it as separate items so the instrumentation specialist can price clearly.
  • Architectural premium hidden in panel supply. If aesthetic is required, name it in the BOQ. Don't expect bidders to guess.
  • No defects-period budget. Quarterly inspection through the defects-correction period (typically 12-24 months) is real ongoing cost. Budget it.